Savage sets a Dec. 7 hearing on $4,397 street assessments for 135 homes
Updated Nov. 17: The City Council ordered the Dec. 7 hearing Monday, Nov. 16, on a voice vote with its consent agenda.
The Savage City Council on Monday, Nov. 16, ordered a Dec. 7 public hearing on its 2027 street project, which proposes assessing 135 homes $4,397 each, payable over 15 years, according to the feasibility report in the meeting packet. The resolution passed on a voice vote with the rest of the consent agenda.
The project is a full depth mill and overlay of about 3.34 miles of streets: Boone, Cavell, Creek View, Flag, Hillsboro, Independence and Zinran avenues, 123rd, 123 Β½, 124th, 125th and 126th streets, and 124th Circle. The subdivisions include Covington Ponds, Schroeder’s Acres and Eagle Creek, along with business parks.
The rate is the 2026 rate raised 2.8% for construction costs. Under the proposed funding plan, assessments, including 36 commercial and industrial properties, cover $1,199,325 of the estimated $5,709,161 cost, and the city’s debt service levy, state aid and its water, sewer and storm water funds cover the rest.
The proposed schedule has a neighborhood meeting Wednesday, Dec. 2, construction from April 26 until it is substantially complete Aug. 20, 2027, and the assessment hearing Oct. 4, 2027. The report recommends owners have trees checked for removal before the work so they do not damage the new pavement. The city’s hazard tree program pays contractors up to $2,500 per property, and owners repay it over five years through a special assessment, a separate staff report says.
What's next: The public hearing will be at 7 pm Monday, Dec. 7, in the Council Chambers at Savage City Hall. The proposed schedule has a neighborhood meeting Wednesday, Dec. 2.